Munson Lakes Office

Downtown Redevelopment & Munson Lakes Office Construction

HL Project Page Banner


New munson office plan 

DESCRIPTION & SUMMARYOld Munson bldg

The City of Howard Lake has acquired a blighted property, acquired grants to assist with the demolition and remediation of contaminated soil. Right-of-way has been established to provide for a multi-modal trial to connect downtown to the Wright County Fair Grounds, Memorial Park and Codger's Cove Campground.

Munson Lakes Nutrition has agreed to purchase the property and construct a new office building to serve their feed mill operations.

JUSTIFICATION

The City has identified this property to redevelop based on specified criteria including increasing investment in the downtown district (Munson Lakes will build a new office), the removal of blighted and vacant property, addressing environmental concerns via remediating contaminated soil and providing an important pedestrian connection from downtown to a key recreational area of the community.

BUDGET IMPACT

Property Acquisition$125,000
Environmental Testing$40,000
Demolition & Soil Corrections$75,000
MN DEED Grant Site Testing$20,000
MN DEED Grant Redevelopment$197,000
Local Tax Dollars in Project$0

TIMELINE (TENTATIVE)

Demolition & Site CorrectionsMarch 2018
Office Construction CommencesMay 2018
Multimodal Trail Construction StartsJune 2018
Multimodal Trail Construction EndsAugust 2018
Office Construction CompletedDecember 2018

PROJECT CONTACT

Nick Haggenmiller
320.543.3670